Home > Operational Area > BOILER
Checking of the Safety Valve Before Circulating fluidized Bed Boiler YG - 75/5.29 - M12 is Started

1. The exhaust steam pipe and drain pipe is complete, smooth and installed firmly.
2. Please check whether the spring and pressure of safety valve is in good condition.
3. Safety valve fittings are complete.    (hxl)